Description of the works
Essential refurbishment work to replace toilet pans in student bedrooms.
Scope of works -
Toilet pan replacement in all 200 en-suite bedrooms
Installation of Altro Whiterock hygienic wall cladding
New bathroom cabinets
Associated plumbing and making good works within the corridor service cupboards.
Phasing & Access -
Works will proceed block by block (approx. 33 rooms per phase)
Carried out with permission of Hall Management
Room access managed in advance with affected building users.
Disruption -
Some localised noise during working hours.
Measures in place to minimise disturbance.
Building Users Notification -
All students and staff have been informed.
Specific notices will be issued ahead of works in each block.
Timescale
14 July to 12 September 2025 (inclusive).
How Can I Get More Information and Help?
The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced as a result of these works.
Spencer Aryeetey - Building Fabric Surveyor
Mobile - 07977004475
Email - s.aryeetey@lboro.ac.uk